Road Stream Crossing Site BL-75
		Crooked River Watershed, Cedar Creek
	
	Camp Petosega Rd
	
		Springvale Twp, 
		Emmet County
	
Information collected by:
	
	
	
	
Site Location
	GPS Coordinates: 45.393778
		, -84.74099
		
		T35N 
		R03W 
		Sec 25
		
	Owned by Local Government
		Fish Passability 1
		Structure is NOT Perched
		
		Total Erosion: 0.0001 tons/year
		
		Severity: Minor
		Year Inventoried: 2004
	Crossing Information
	Type of Crossing: Bridge
		
		Structure Shape: Open Bottom Square/Rectangle
		Inlet Type: Other
		Outlet Type: Outlet Apron
		Structure Material: Wood
		Structure Substrate: Mixture
		General Conditions: Good
	Multiple Culverts/Spans  | ||||
Culvert/Span  | Width  | Length  | Height  | Material  | 
1  | 
			24 ft.  | 
			15.5 ft.  | 
			5 ft.  | 
			Wood  | 
		
Structure Interior: smooth
	
	Dimensions of Structure: Length 14.5 ft.
		, Width 24 ft.
		, Height 5 ft.
	
	
	
		
		
		
	
	
	
		
		
		
	
	
	Structure is NOT Perched
	
Structure Inlet
		Water Depth: 2.45 ft.
		Embedded Depth of Structure: 0 ft.
		Water Velocity*: 1.3 ft./sec.
		Structure Outlet
		Water Depth: 2.33 ft.
		Embedded Depth of Structure: 0 ft.
		Water Velocity*: 1.6 ft./sec.
		
	*Water Velocities were measured 0.5 ft. below Surface
	
	 (with Meter)
Additional Comments
Camp Petasega
Stream Information
	Stream Flow: Bankfull
	
	
		
		
	
	
		
		
	
Riffle Information
Water Depth: 1.55 ft.
	Bankfull Width: 25 ft.
	Wetted Width: 25 ft.
	Water Velocity: 0.9 ft./sec.
	 (Measured with Meter)
	
	Dominant Substrate: Sand
Road Information
	
	Paved 
	Private Road
	
	
	
	Road Condition: Good
	Road Width at Culvert: 15 ft.
	
	Location of Low Point: Other
	Runoff Path: Roadway
Fill Depth: 0 ft.
		Slope: More than 1:2
	
	
		
		Fill Depth: 0 ft.
		Slope: More than 1:2
	
Approaches
		Left Approach
		Length: 2 ft.
		 Slope: Less Than 1%
		Vegetation: None
		LS Factor: 0.05
		Erosion: 0 tons/year
		Right Approach
		Length: 2 ft.
		Slope: Less Than 1%
		Vegetation: None
		LS Factor: 0.05
		Erosion: 0 tons/year
		Erosion Information
	Total Erosion at Crossing: 0.0001 tons/year
	
	Erosion is occurring and corrective actions can be installed to address the problem.
	
Summary Information
	Fish Passability 1
	
	
	
	
	
	